With the rapid development of the construction industry
The increasing demand for sand and gravel
Artificial sand replacing natural sand is an inevitable trend
Therefore, sand washing equipment will be an important equipment for artificial sand production lines
1. Before installation, check if all components are complete and if there is any damage The equipment's Sex.
2. Based on the specific situation on site, design the basic construction drawings and firmly install the fine sand recycling machine on a solid concrete foundation.
3. The installation of the spiral fine sand recycling machine must follow the requirements of the installation diagram Tilt angle.
The motor of the fine sand recycling machine needs to be installed on the guide rail to adjust the tightness of the belt. The belt pulley and motor pulley should be installed during installation parallel.
5. After adjusting according to the above requirements, rotate the rotor disc a few times to check for any jamming or collision.
When the sand washing machine is in use
Must undergo trial operation
Empty load operation debugging of fine sand recycling machine
After the motor is started, the sand washing machine should run smoothly without any abnormal vibration.
2. The temperature rise of the bearing shall not exceed 35 ℃.
3. The sand washing machine should run idle for 2-4 hours. Check for loose connections at all points and adjust them accordingly.
Load operation debugging of fine sand recycling machine
1. The fine sand recovery machine can only undergo a load operation test after a good no-load test run.
2. The fine sand recycling machine should operate smoothly without any abnormal vibration.
3. The temperature rise of the bearing shall not exceed 40 ℃.
4. No dust is allowed to enter each sealed area.
5. Measure the actual power of the motor without any abnormal fluctuations.
6. The load operation test needs to be conducted continuously for 5-6 hours. Only after the operation is confirmed to be normal and error free, can it be officially put into use.
Operation precautions
The device is functioning normally
The fine sand recycling machine can only operate
Before starting the device, check if there are any debris in the drainage hole and clean it up in a timely manner.
2. Carefully check whether all fasteners are fully tightened and whether the nuts are tightened.
3. Check if the lubricating oil has reached the height, and if not, add lubricating oil in a timely manner.
4. Check if the belt is in good condition and replace it if it is damaged.
5. Check if the protective device is in good condition, if not The phenomenon should be promptly eliminated.
If any abnormal phenomenon is found after starting the fine sand recovery machine, it should be stopped immediately. Only after troubleshooting can it be restarted.
7. The fine sand recycling machine is allowed to start under no-load conditions.
When washing sand, the flushing water pipe should be released first, and the direction of water spraying and the height of the overflow baffle should be adjusted at the same time. The water supply should be moderate, both Clean the sand thoroughly without causing sand to overflow along the groove. When adding materials, pay attention to adding them evenly to avoid damage to the equipment due to overload.
When stopping the fine sand recycling machine, it should be carried out in the order of the process, and it is forbidden to stop the machine with materials or continue feeding after stopping.